AfterHow long does a kitchen remodel take in Plano, TX? Plan on 10 to 16 weeks for a mid-size kitchen.
A standard mid-size kitchen remodel in Plano runs 10 to 16 weeks from permit approval to final inspection, and the permit and inspection holds built into that schedule account for roughly three to four of those weeks. Cabinet and countertop lead times can push a larger job to 18 or 20 weeks. The honest timeline starts on permit-approval day, not demo day, and in Plano that’s a window you can actually plan around. If you want your own job mapped against that calendar, call (877) 382-4108 and we’ll talk through it.
Plano’s housing stock shapes this more than most homeowners expect. Most homes here were built between the 1970s and 1990s, and by the 1990s the city was largely built out. That means almost every kitchen we touch is a renovation inside a 30-to-50-year-old house with brick veneer, slab-on-grade foundation, and the original plumbing and wiring behind the walls. The framing is generally sound, but the surprises live in what the last remodel hid. And this is where the City of Plano’s inspection sequence, not the pace of the crew, sets your actual finish date. Plenty of useful detail lives on our Kitchen Remodeling in Plano page; here we’re focused on the clock.

The permit and inspection sequence that actually sets your timeline
Here’s the part most timeline articles skip: inspections create mandatory holds. Work stops while you wait, and no amount of hustle gets around it. Drywalling over uninspected rough-in is how kitchens get torn open a second time.
- Permit application to city review: typically 5 to 10 business days for a standard kitchen in Plano. Add time if the plan touches structural walls or moves a gas line.
- Rough-in inspection hold: electrical, plumbing, and HVAC rough-in must all be inspected and signed off before drywall closes the walls. This is usually a 1 to 3 day hold once your turn comes up.
- Final inspection: scheduled after cabinets, countertops, and fixtures are in. Another hold day or two, and it’s the one that matters most for resale and insurance.
Every inspection is a planned stop. A responsible contractor schedules around the inspector’s calendar and builds the hold into the written schedule instead of guessing. Tom Barrett has pulled Plano permits since 1998, and the reason he still likes the permit inspector is simple: that inspector works for you, not for us.
Phase-by-phase calendar for a mid-size Plano kitchen
This is the rhythm we build on for a typical Plano job in the $14,000-$45,000 range, where cabinets, countertops, and some layout work are all in scope. Expect your own calendar to shift with the lead times below.
| Phase | Typical duration | What’s happening |
|---|---|---|
| Permit + city review | 1-2 weeks | Application, plan check, approval before demo |
| Demo and tear-out | 2-4 days | Cabinets, countertops, flooring, fixtures removed |
| Rough-in (electrical, plumbing, HVAC) | 1-2 weeks | New circuits, supply/drain lines, venting |
| Rough-in inspection hold | 1-3 days | Inspector signs off before walls close |
| Drywall, tape, texture, paint | 1-2 weeks | Walls closed, finish work begins |
| Tile and backsplash prep | 3-5 days | Floor tile, shower or wall tile if in scope |
| Cabinet installation | 3-5 days | Boxes set and leveled |
| Countertop template + fabrication | 2-3 weeks | Template after cabinets are set, then fabrication |
| Countertop install + appliance delivery | 3-7 days | Countertops set, appliances dropped in |
| Final inspection + punch list | 3-7 days | Sign-off and the small fix list |
Add those weeks up and you land right around the 10-to-16-week floor. On a smaller kitchen in the $9,000-$20,000 range, the same sequence compresses to 6 to 10 weeks because there’s less rough-in and less finish.

Countertop fabrication is the window that stalls “almost done” kitchens
The most common reason a Plano kitchen remodel sits “almost done” for two extra weeks is the countertop. Cambria and quartz fabrication can’t start until your cabinets are set and level, because the template is cut to the actual cabinet footprint. From that template, fabrication typically takes 2 to 3 weeks. That window is non-negotiable.
So we order the countertop against the cabinet-set date, not against demo day, and we tell you upfront that this is the phase where patience pays. Countertop installation itself runs $2,000-$6,500 depending on material and square footage, and that lead time is baked into the schedule you sign.
A word on sequencing: never let a crew drywall over rough-in before the inspection is signed. It saves a day, then costs you a month. Our crews are background-checked and carry the Barrett & Sons name, and every eligible job gets permits pulled and inspections signed. The home base of our work runs on that rule, because the last contractor most folks hired told them permits were optional.
Scheduling a kitchen in a North Texas summer
If your remodel touches an exterior wall, adds a window, or extends into an addition, summer changes the math. June through August in North Texas runs crews shorter days in the heat, and exterior phases stretch accordingly. A July start on a kitchen with a new window and exterior wall work can add a week or two to the back end compared with a February start. We build that into the schedule rather than quoting dry-season pacing and then apologizing for it in August.
Those same conditions shape the whole trade here. The expansive clay soil under most Plano slabs means foundation movement is common, so we check for settled floors or cracks before we set cabinets and level the run. Severe spring hail drives exterior replacement calls, and a storm can push your exterior punch items behind schedule if you start in spring. It’s a real local pattern; a contractor who doesn’t plan for it is quoting you a timeline from somewhere else.
What a written schedule from us looks like
At contract signing you get a phase-by-phase timeline with every inspection hold marked as a planned stop, not a surprise. Alongside it sit the scope, allowances, and change-order terms in writing. An allowance that isn’t on paper is a surprise waiting for a date. If a scope change comes up mid-job, you get a written change order before a single nail moves.
Every completed job is backed by our written 90-Day Done Right Promise: if something isn’t done right, one call brings us back. We also offer free second opinions on any written estimate, $40 off any repair over $200, no trip charge inside Collin County, and a permanent 10% Senior & Veteran discount. For the full scope of what we do across trades, see our Kitchen Remodeling service page.
FAQs
Ten to sixteen weeks for a mid-size kitchen, with permit approval and inspection holds eating three to four of those weeks before any cabinetry is set. Smaller kitchens in the $9,000-$20,000 range often finish in 6 to 10 weeks. Call (877) 382-4108 for a free estimate mapped to your scope.
No. Skipping the rough-in inspection doesn’t save time; it creates a failure you’ll pay to fix. Electrical, plumbing, and HVAC must be inspected before drywall closes, and working around the hold is how a kitchen gets torn open twice. Call (877) 382-4108 and we’ll explain what your job actually needs.
Because Cambria and quartz get templated from your set, level cabinets, then fabricated to that exact template, usually 2 to 3 weeks. It’s the most common reason a kitchen looks finished but isn’t. A free estimate from us will show that window on paper, so you can plan around it. Call (877) 382-4108.
Fall through spring is generally faster if your kitchen touches an exterior wall or adds a window, because June through August heat compresses outdoor work and stretches those phases. We build the real season into the schedule instead of promising a summer start will run at the same pace. Call (877) 382-4108 for exact timing on your job.
If you’d rather have your own kitchen timeline laid out by someone who’ll pick up the phone and answer for it, Barrett & Sons Construction Plano offers a no-pressure assessment in Plano. We’re owner-operated, founded in 1998, and a live person answers 24 hours a day. Call (877) 382-4108 for a free estimate.
Written by the team at Barrett & Sons Construction Plano, serving Plano, TX.